Roger B let me have the following report on activities back on site at Broadway.
Hi Bill,
There were 10 people on-site today.
JC & Bob W worked all day on the Signal Box and added
another course of Blues.
There were 2 Brick Cleaners beavering away.
The remainder of the team, Peter H, Steve, Gord, Tony B,
& I moved 5 Dumper loads of Drainage blocks South, some 100 plus blocks.
before Richards arrival. I estimate that this is half of the blocks required for
1C.
It would be useful if we could move the remainder of the
blocks South in the next 2 weeks prior to the commencement of block laying.
On the platform 2 slab laying front we laid 15 slabs
today which was a great team effort.
To date we have laid 29 slabs and I estimate there are 12
slabs left to lay.
Given good weather & Richards availability next
Wednesday we will complete platform 2 slab laying.
Roger
So that was Wednesday - as I say a great effort on everyone's part - now for Thursday and Friday!
No comments:
Post a Comment