What a good day the weather was gloomy from time to time, but 28 Volunteers and the GM Contrators spent a really productive day on Site.
Firstly, the centre track drain was finished off
exactly to specification and a great job was done. In addition the two side catch pits adjacent to the one in the photo were cleaned out in anticipation of lateral connections being made.
At the same end of the site work was started on slabbing up the rear of platform 1C. As I've said before, this is definitely a three Weetabix a day job!
Here Steve, Dave and Roger toil with the barrowing of the slabs. How well they look in their finished locations.
On the opposite side the block laying on 2C was proceeding at a pace. Here Martin, Clive and Peter have started the 100 mm blocks. In the background Roger B is setting up the next section.
Of course none of activities above would be possible without the hard work of the muck mixing crew. Here Keith and Paul stuck to the task most of the day.
At the southern end of the site some more work was completed on the Signal Box. Here joist trimmers are being bolted together.
We have also invested in a new mitre saw for continuing with the carpentry. There is nothing like a new piece of equipment to draw a crowd. Here Tony and Peter Q are about to give it a road test.
On the opposite side of the trackbed the comms ducting was laid across the driveway. Here Gord and Dave bed the ducting in before cover with ballast.
Up on the station/driveway fence line Jim H was making some nifty secure sockets to put the fence posts in. This is being carried out specifically for the necessary maneuvering to get the centre span of the footbridge onto site. In the longer term it will be used to get plant and materials into position for the station construction.
Mid morning we had a delivery of pallisade fencing which required hand loading into secure storage. Dave B and a crewe were undertaking this and I think they all had longer arms by the end of the day!
Last but by know means least a team were working on the fabrication of a booth (the Spruce Goose) to act as weather protection and sand blasting containment for the footbridge span. Ian Vic and Peter in action on this tricky bit of carpentry.
Roger Brindley was Duty Officer for the day and he sent me the following report wich covers some of the achievement statistic of the day
Firstly, the centre track drain was finished off
exactly to specification and a great job was done. In addition the two side catch pits adjacent to the one in the photo were cleaned out in anticipation of lateral connections being made.
At the same end of the site work was started on slabbing up the rear of platform 1C. As I've said before, this is definitely a three Weetabix a day job!
Here Steve, Dave and Roger toil with the barrowing of the slabs. How well they look in their finished locations.
On the opposite side the block laying on 2C was proceeding at a pace. Here Martin, Clive and Peter have started the 100 mm blocks. In the background Roger B is setting up the next section.
Of course none of activities above would be possible without the hard work of the muck mixing crew. Here Keith and Paul stuck to the task most of the day.
At the southern end of the site some more work was completed on the Signal Box. Here joist trimmers are being bolted together.
We have also invested in a new mitre saw for continuing with the carpentry. There is nothing like a new piece of equipment to draw a crowd. Here Tony and Peter Q are about to give it a road test.
On the opposite side of the trackbed the comms ducting was laid across the driveway. Here Gord and Dave bed the ducting in before cover with ballast.
Up on the station/driveway fence line Jim H was making some nifty secure sockets to put the fence posts in. This is being carried out specifically for the necessary maneuvering to get the centre span of the footbridge onto site. In the longer term it will be used to get plant and materials into position for the station construction.
Mid morning we had a delivery of pallisade fencing which required hand loading into secure storage. Dave B and a crewe were undertaking this and I think they all had longer arms by the end of the day!
Last but by know means least a team were working on the fabrication of a booth (the Spruce Goose) to act as weather protection and sand blasting containment for the footbridge span. Ian Vic and Peter in action on this tricky bit of carpentry.
Roger Brindley was Duty Officer for the day and he sent me the following report wich covers some of the achievement statistic of the day
Hi Bill
A very productive day from the Platform Teams.
Platform 2c, 14 Blocks were laid to complete the Block
Laying task.
This task was then completed by in filling them with
concrete.
On Platform 2c the Drain Pipe was laid and completed
using an in fill of Pea Gravel.
Once the pipe was laid, Steve Warren of JCB fame provided
the back fill to complete 2c.
Also on Platform 2c, 50 metric blocks were laid on the
first course.
Platform 1c 12 3x2
retaining slabs were concreted in.
Finally Steve Warren did a superb job in completing the
Central Drain while at the same time assisting with other tasks across the
site.
We are very fortunate to have such a very skilled,
adaptable and enthusiastic JCB operator as Steve to work with us at Broadway.
Big thanks to all of the team ( to numerous to mention)
who worked across the all of the various Platform projects today.
We certainly moved the Broadway Project forward to day by
having lots of enthusiasm and great team work.
Regards
Roger
I echo Roger's sentiments on the camaraderie and team spirit of the Broadway Area Group - it is second to none. My thanks to everyone for their efforts today.
6 comments:
Hello Bill,
Another amazing report, and tremendous effort from the volunteers!
So, a quick question, when the platforms are built and the signal box is weathertight, will the P/W start laying track? Could you have a functional trackbed, while you are building the station building, not for passengers, but maybe for building materials etc?
Thanks,
Its a nice idea but you need maximum accessibility/flexibility during the whole construction phase for plant movement, deliveries and material storage.
as always, a joy to read. you are making fantastic progress. thank you.
Bill you are so lucky to be able to build a station without trains and track, at work I have to build things with trains and track and it a pain.
Great work by the BAG team
On your report you mentioned the slabbing of '2c'. I looked at the photo and thought I must be losing it (not to be ruled out by the way!).
Luckily Roger confirms it was 1c. Perhaps amend your blog entry.
Coming up in a week or two, looking forward to it.
Just keeping you on your toes....