I have had a couple of questions about our future plans. We do, of course have a detailed master plan, which is very much dependant on funding, planning approval, and the GWR Board signing off the steps along the way.
However, the following is immediately before us - I hope this helps:-
However, the following is immediately before us - I hope this helps:-
September 2012
Complete Ashchurch Recovery
Complete Taunton Recovery
Complete coping slabs on 1B
Fit lampposts to 1B (4 off)
Fit lampposts to 1B (4 off)
Extract and re-lay Mains cable
Lay Platform 2 Foundations (60M)
October 2012
Start Platform 2 Wall
Complete Phone Box