Thursday 30 August 2012

Next Steps

I have had a couple of questions about our future plans. We do, of course have a detailed master plan, which is very much dependant on funding, planning approval, and  the GWR Board signing off the steps along the way.

However, the following is immediately before us - I hope this helps:-

September 2012

Complete Ashchurch Recovery

Complete Taunton Recovery

Complete coping slabs on 1B
Fit lampposts to 1B (4 off)

Extract and re-lay Mains cable

Lay Platform 2 Foundations (60M)


October 2012

Start Platform 2 Wall

Complete Phone Box

Complete coping slabs 2A


 

 

1 comment:

richard said...

In the words of Colonel John "Hannibal" Smith I love it when a plan comes together. Defiantly "A" Team work at Broadway