Tuesday 23rd July 2013 Platform 2B

No pictures today I'm afraid, but very much worthy of a post all the same. John Crawford  spent the morning  preparing the trench and the shuttering, in order to start the concrete pour  for the 2B footings. When in place, Graham Morrison assisted John in taking delivery  of two loads of concrete from Hansons. This was poured, levelled and tamped to a length of 14m and by 15:30 this section was complete.

The rest of the job, with a good following wind, will be completed on Thursday and Friday of this week, ready for block laying to start next week.

Thanks John and Graham - photos tomorrow.......